Fulton County, IN
Zoning in Fulton County, Indiana: A 500-Megawatt Data Center Proposal and a 12-Month Moratorium
A single proposed project -- a 300-acre data-center campus near the town of Akron -- pushed Fulton County's zoning process further and faster than almost anything else in the county's recent history. Here's the confirmed sequence of votes and what remains unresolved.
This page covers what's specific to Fulton County. For the general explanation, see the national guide.
The trigger: a proposed 500-megawatt data-center campus near Akron
In late 2025 and early 2026, a developer called the Decennial Group unveiled plans for a roughly 300-acre, 500-megawatt data-center campus near the town of Akron in Fulton County. Decennial pitched the project to county officials as an economic opportunity of real scale for a county this size: $100 million to $150 million in projected revenue over 15 to 20 years, against a county budget that currently runs around $16 million a year, plus 100 to 150 jobs once the facility came online. The company hosted a series of public question-and-answer sessions to try to build local support as the proposal moved toward formal review.
Those sessions did not settle the debate. As word spread, resident turnout at Fulton County Commissioners and Area Plan Commission meetings grew large enough that one meeting had to be held at the Fulton County Sheriff's Department to accommodate the crowd. The core objections tracked what's become a familiar pattern in Indiana's recent wave of data-center fights: concern over how much water and electricity a facility of this scale would draw, and what a 24/7 industrial-scale operation would do to a rural area's character and infrastructure.
The Area Plan Commission recommendation, then the Commissioners' vote
The Fulton County Area Plan Commission took up a proposed moratorium on new data-center proposals and, after a standing-room-only public hearing, voted 6-1 on February 10, 2026 to recommend that the Fulton County Commissioners adopt it -- a lopsided vote that reflected how much public opposition had built by that point. The Fulton County Commissioners followed with their own vote on the moratorium in early March 2026, approving it 2-1, effectively pausing the Decennial proposal and any other new data-center application countywide for twelve months while the county studies the issue further.
As part of adopting the pause, the county set up a process for a data-center study committee to research how similar projects have played out economically and environmentally in comparable communities elsewhere -- rather than simply letting the moratorium run out and defaulting back to whatever the prior ordinance allowed. That's a meaningfully different approach than a moratorium adopted purely to buy time without a defined next step, though this research pass could not confirm the study committee's membership, timeline, or any findings it may have produced since.
What's confirmed, and what isn't, as of this review
What's solidly confirmed, across multiple independent news outlets (WNDU, ABC57/WSBT, and the trade publication Data Center Dynamics) plus a posted legal notice through the Rochester Sentinel: the Decennial Group's proposal, the scale of public opposition, the February 10, 2026 Area Plan Commission recommendation vote (6-1), and the Commissioners' adoption of a 12-month moratorium in early March 2026 (2-1). What isn't confirmed in this research pass: the moratorium's exact expiration date and whether it has since been extended, allowed to lapse, or replaced with permanent data-center-specific zoning standards; whether the Decennial proposal itself was formally withdrawn, is still pending for reconsideration once the moratorium ends, or has moved to a different site; and any findings from the county's planned data-center study committee.
If you're evaluating land anywhere near Akron, or anywhere in Fulton County that a large-scale industrial user might target for its rural land, cheap power access, or highway proximity, confirm the moratorium's current status directly with the Fulton County Plan Commission before assuming either that a data center is definitely off the table or that it's simply paused and will proceed once the year is up -- both outcomes remain genuinely possible based on what's publicly confirmed as of this review.
Ready to talk to someone who knows land?
Tell us what you're trying to do and we'll connect you with a local land specialist -- someone who understands zoning, perc, and access, not just listings.
Connect with a local land specialistSources
- Fulton County approves 12-month data center moratorium after heated public hearing — WNDU (accessed 2026-09)
- Fulton County data center moratorium heads to county commission vote — WNDU (accessed 2026-09)
- Fulton County commissioners approve one-year moratorium on data center construction — WNDU (accessed 2026-09)
- Officials recommend data center moratorium for approval in Fulton County, Indiana — Data Center Dynamics (accessed 2026-09)
- Latest details on potential data center development in Fulton County — ABC57 (accessed 2026-09)
- Developer unveils data center plan in Akron amid resident concerns — ABC57 (accessed 2026-09)
- Data center rumors fuel massive turnout during Fulton County Commissioners meeting — WSBT (accessed 2026-09)
- Commissioners vote 2-1 in favor of 12-month data center moratorium — Rochester Sentinel (accessed 2026-09)
Last reviewed 2026-09