Wind Energy Leasing in Hardin County, Iowa

Most Iowa wind stories are about a project moving through permitting or already generating power. Hardin County's is different: a Board of Supervisors moratorium has blocked new commercial wind turbine permits since December 2019, stalling a proposed 200-megawatt project for years, even as at least one city inside the county has voted to support it. Here's what's actually on the record, and what to verify before assuming a wind lease is -- or isn't -- realistic on Hardin County land.

This page covers what's specific to Hardin County. For the general explanation, see the national guide.

December 2019: a 3-0 vote for an indefinite moratorium

In December 2019, the Hardin County Board of Supervisors voted 3-0 to impose an indefinite moratorium on issuing building permits for commercial wind turbine construction. Coverage of the vote attributed it to a specific set of concerns rather than blanket opposition to wind energy: drainage systems that could be affected by turbine construction and access roads, potential interference between turbines and a newly installed county 911 emergency communications system, and the absence of a clearly defined plan for decommissioning turbines once they reach the end of their useful life. Unlike a fixed-term pause, this moratorium was indefinite from the start -- it would remain in place until the county affirmatively acted to lift or modify it.

The stalled project: 200 MW, up to 84 turbines, Alden to Radcliffe

The moratorium's immediate practical effect was to stop a specific proposal: RWE Renewables had been planning a 200-megawatt wind farm on the county's west edge, potentially including as many as 84 turbines, running from an area west of the town of Alden south to near Radcliffe. Coverage of the project estimated it could generate roughly $50 million in tax revenue over a 30-year project life, potentially making it one of the largest annual taxpayers in the county -- a meaningful number for a rural Iowa county's budget, and the kind of figure that explains why the project has stayed a live topic even while blocked.

In the months after the moratorium passed, county supervisors discussed conditions under which it might be lifted, including a proposed half-mile setback requirement between turbines and neighboring dwellings -- stricter than many Iowa county wind ordinances. Separately, at least one city within the county, Iowa Falls, passed a resolution in support of the RWE project even as the county-level moratorium kept it from moving forward, illustrating a real split between municipal and county-level appetite for the project.

Where things stand: a moratorium now stated to run to 2030

As of this review, reporting and regional commentary consistently describe Hardin County's wind moratorium as still in effect, with a stated end date of 2030 -- more than a decade after it was first imposed. This research could not independently confirm the exact date or vote details of whatever county action set that specific 2030 end date (as opposed to the original 2019 indefinite moratorium), so treat the 2030 figure as the best available current information rather than a fact independently verified from a primary county document. Hardin County's 1999 zoning ordinance separately includes an article addressing non-commercial and commercial wind energy systems, which would govern any future turbine permitting once (or if) the moratorium is lifted or modified.

What to verify before treating a Hardin County parcel's wind potential as real

  • Current moratorium status directly with Hardin County Planning and Zoning ((641) 849-7372) -- whether it remains in force, whether the county has moved toward a permanent wind energy ordinance (with or without a half-mile setback), and whether any application has been accepted despite the general moratorium.
  • Whether a specific parcel sits within the RWE-proposed Alden-to-Radcliffe corridor, elsewhere in the county, or outside any documented project area -- reporting describes a general corridor, not a parcel-level map.
  • Whether RWE Renewables (or another developer) still holds the project, given how long the moratorium has been in place -- confirm directly with RWE rather than assuming the original 2019-era company and project scope are unchanged.
  • Any existing wind-related option or easement recorded against a specific parcel, via the Hardin County Recorder -- a signed option from before the moratorium may still be outstanding even though construction has not proceeded.
  • The zoning ordinance's wind energy systems article for baseline setback and permitting standards that would apply once the moratorium is lifted or modified, separate from whatever additional conditions supervisors may still be negotiating.

Ready to talk to someone who knows land?

Tell us what you're trying to do and we'll connect you with a local land specialist -- someone who understands zoning, perc, and access, not just listings.

Connect with a local land specialist

Sources

  1. Hardin County supervisors approve moratorium on wind turbine permits — KCRG (accessed 2026-09)
  2. Hardin County passes indefinite moratorium on building permits for wind turbines — WeAreIowa (accessed 2026-09)
  3. Indefinite moratorium passed over Hardin County wind turbines — WeAreIowa (accessed 2026-09)
  4. Cities throw support behind wind farm as county moratorium remains in place — Times Citizen (accessed 2026-09)
  5. In Iowa, conservative group looks to counter local wind, solar opposition — Canary Media (accessed 2026-09)
  6. Zoning Ordinance & Maps — Hardin County, Iowa Government (accessed 2026-09)

Last reviewed 2026-09