Dade County, MO

Wind and Solar Leasing in Dade County, Missouri

Dade County is already home to part of an operating wind farm and is the site of a much larger one now in development -- and because the county has no zoning, neither project has gone through a public rezoning hearing. Here's what's actually happening on the ground, and what the absence of a zoning process means for a landowner considering a lease, or living next to one.

This page covers what's specific to Dade County. For the general explanation, see the national guide.

Two projects, two stages: what's actually built vs. what's still in development

It's worth being precise about which project is where in its lifecycle, since the two carry very different implications for a land buyer. Kings Point is a completed, operating project: 69 turbines, commissioned by Liberty Utilities (the successor to Empire District Electric) in April 2021, spanning four counties -- Barton, Dade, Jasper, and Lawrence -- near Golden City and Lockwood. If your parcel is within or adjacent to that footprint, the turbines, access roads, and transmission lines are already built and operating; due diligence here is about visiting the site and assessing noise, shadow flicker, and viewshed impact directly rather than researching a future risk.

Buffalo Branch is different: a 247 MW project across roughly 17,000 acres of private land near Lockwood and Greenfield, still in active development. NorthRenew Energy originally developed the project; BluEarth Renewables, a Canadian renewable-energy developer, acquired it in February 2022 and has continued advancing it toward construction, with an expected online date reported around 2029. A project still years from construction means lease terms, turbine layouts, and access-road routing could all still change -- if you're being approached for a lease here, or buying land near the reported project footprint, expect a longer runway of uncertainty than you would with an already-operating project like Kings Point.

What "no zoning" actually changes about the process

Dade County has never adopted Chapter 64 zoning, so a wind project of this scale faces none of the conditional-use-permit or rezoning process a zoned county would require -- no public hearing before a planning and zoning commission, no county-commission sign-off on land use. A lease and a project can move from signed agreement to construction with essentially no public review beyond whatever road-use or right-of-way agreement the developer negotiates directly with the County Commission for construction traffic and any transmission-line routing across county roads.

That cuts both ways for a land buyer. If you want to lease your own land for wind, there's no zoning approval standing between you and a signed contract -- the process is faster and less bureaucratic than in a zoned county. If you're buying land near, but not part of, a wind project, you have no zoning hearing to attend, no notice requirement to rely on, and no variance process to challenge -- your leverage is a private conversation with the neighboring landowner, the developer, or the County Commission directly.

MU Extension publishes general Missouri guidance on leasing land for wind and solar energy development (lease structure, decommissioning obligations, land restoration at end of lease, easement stacking, and tax implications) that is worth reading regardless of which county you're in -- it is not Dade County-specific, but it covers questions that apply directly to a lease offer here, particularly given that one project (Buffalo Branch) is still years from construction and lease terms may be negotiable in ways they no longer are for an already-built project like Kings Point.

Lease-rate context and what to ask before signing

General Missouri and national wind-industry figures (not Dade County-specific, since no county-level lease-rate dataset is public) put wind-turbine lease payments in a wide range depending on the specific structure -- some leases pay a flat annual per-turbine fee, others pay per-acre or a royalty tied to power generated, and access-road and transmission-corridor easements on non-turbine parcels are typically compensated separately and at lower rates than the turbine-pad parcels themselves. Only a small fraction of a leased parcel (often well under an acre per turbine, plus access roads) is actually taken out of agricultural production, which is part of why wind leases are attractive to working farms and ranches -- but the easement itself, and any associated transmission-line rights, can run for the life of the project (often 30+ years) and can be difficult to unwind even after decommissioning.

Before signing anything -- whether you're approached for Buffalo Branch or a future project -- have a Missouri-licensed attorney experienced in reviewing wind and solar leases go through the decommissioning bond or security requirement (who pays to remove a turbine and restore the land if the project is abandoned or reaches end-of-life), how the lease affects your property-tax assessment, whether the easement survives a sale of the underlying land, and how neighboring parcels' setback and noise obligations are handled if you are not the one leasing. Given that Dade County has no local siting ordinance to fall back on, these lease-specific terms are the only real protection a landowner has.

Ready to talk to someone who knows land?

Tell us what you're trying to do and we'll connect you with a local land specialist -- someone who understands zoning, perc, and access, not just listings.

Connect with a local land specialist

Sources

  1. Liberty Utilities building new wind farm in Jasper, Dade, Lawrence and Barton Counties — KY3 (accessed 2026-09)
  2. Kings Point Wind Project, Barton, Dade, Jasper and Lawrence Counties, Missouri — Missouri Public Service Commission (accessed 2026-09)
  3. Wind Farms — Liberty Utilities (accessed 2026-09)
  4. North Fork Ridge Wind Farm / Kings Point Fact Sheet — Tenaska (accessed 2026-09)
  5. Kings Point, Missouri — Wikipedia (accessed 2026-09)
  6. BluEarth Acquires 247 MW Wind Development Project in Missouri — BluEarth Renewables (Newsfile) (accessed 2026-09)
  7. BluEarth acquires Missouri wind project from NorthRenew — PE Hub (accessed 2026-09)
  8. Buffalo Branch Wind Project — BluEarth Renewables (accessed 2026-09)
  9. Buffalo Branch Wind and Solar LLC -- Dade, Missouri — CleanView (accessed 2026-09)
  10. Buffalo Branch Wind — Global Energy Monitor (accessed 2026-09)
  11. Introduction to Wind Energy Leases (G432) — University of Missouri Extension (accessed 2026-09)
  12. Leasing Land for Solar Energy Development (G431) — University of Missouri Extension (accessed 2026-09)

Last reviewed 2026-09