Wind and Solar Leasing on Fisher County Land

Fisher County isn't a speculative wind-lease market -- it has an 18-year operating history spanning two distinct projects. That history is useful for a landowner precisely because it means there's real precedent to check, from lease terms to decommissioning, rather than a developer's first pitch in a brand-new county.

This page covers what's specific to Fisher County. For the general explanation, see the national guide.

Two projects, two different eras of Texas wind development

Fisher County's wind history splits into two distinct chapters. The Roscoe Wind Complex, which began operating in 2008, was built across roughly 100,000 leased acres spanning four counties -- Fisher, Mitchell, Nolan, and Scurry -- on land that had mostly been dryland cotton farming. At 627 turbines and 781.5 megawatts, it was among the largest wind farms in the world when built, and it has now been running long enough (18 years as of 2026) that decommissioning, repowering, and lease-renewal questions -- not just initial construction -- are live issues for landowners under those original leases. The complex's combined four-county local tax contribution has topped $92 million since 2008, a figure that reflects the whole complex rather than Fisher County's individual share.

Mesquite Star, by contrast, is a newer project: 419 megawatts across 118 turbines, developed by Clearway Energy Group and completed in 2020, with 34 miles of new roads and collection infrastructure. Clearway's own materials describe it as a Fisher County project, but independent power-plant location databases place its address or interconnection point in neighboring Nolan County, or describe it as straddling both counties -- this research could not resolve the conflict with confidence, so treat the project's exact county footprint as unconfirmed rather than settled, and if you're evaluating land specifically because of proximity to Mesquite Star, verify which side of the county line the turbines and any lease-relevant infrastructure actually sit on. Its power is sold under long-term agreements to named corporate and institutional buyers -- Ecolab, Lowe's, Intuit, and Brown University among them -- rather than into the wholesale market alone, which is a structurally different (and generally more stable, long-horizon) revenue arrangement for the developer than a merchant-market project, though that structure affects the developer's economics more directly than an individual landowner's lease terms.

What an 18-year operating history actually gives a landowner to check

The practical value of Fisher County's wind history for a prospective buyer isn't just that wind leasing happens here -- it's that there is real precedent to investigate. A parcel near or within the Roscoe Complex's footprint likely already has neighboring turbines, access roads, and collection lines in place, which affects both nearby land's own wind-development potential (setback and spacing rules a new project must respect relative to existing turbines) and its general character as a working landscape rather than open range. For a parcel actually under an existing wind lease -- whether inherited with the purchase or newly negotiated -- Fisher County's older Roscoe-era contracts are old enough that decommissioning and end-of-lease-term obligations are worth scrutinizing specifically, since a lease signed in the mid-2000s may handle turbine removal, land restoration, and financial assurance for decommissioning very differently than a lease Clearway would draft today for a new project.

For a buyer being pitched a new wind or solar lease on Fisher County land, the county's wind history is a resource for due diligence, not a guarantee of similar terms: ask specifically which company operates the nearest existing turbines and whether that company (or its successor, since wind assets are frequently sold between owners) is the same one making the current offer, request the actual per-acre or per-turbine royalty structure rather than an advertised range, and have any decommissioning-bond or land-restoration language reviewed by a Texas real estate or energy attorney experienced with wind leases specifically -- not a generalist. Because none of the county's OSSF, subdivision, or floodplain rules covered on the hub are wind-specific, they still apply independently to any residence, access road, or other structure a landowner might add alongside a wind lease.

Before signing a wind or solar lease on Fisher County land

  1. Identify which specific company currently operates the nearest turbines (Roscoe-area assets have changed hands since 2008; Mesquite Star is operated by Clearway) and confirm the identity and track record of the company actually offering a new lease.
  2. Request the complete royalty and payment structure in writing, not just an advertised per-acre or per-megawatt range, and have it reviewed against comparable Fisher County terms if any can be found through neighboring landowners or a local attorney.
  3. Ask specifically about decommissioning obligations, financial assurance (bonding), and land-restoration standards at end of lease term -- more relevant in a county with an 18-year-old project than in a brand-new wind market.
  4. Confirm how a wind lease interacts with any existing mineral lease or agricultural use on the same land, since Fisher County land has a long history of both cotton farming and, in places, oil and gas activity.
  5. Have a Texas attorney with wind/solar lease experience specifically (not a general real estate attorney) review easement scope, term length and renewal options, and any exclusivity or non-compete language before signing.

Ready to talk to someone who knows land?

Tell us what you're trying to do and we'll connect you with a local land specialist -- someone who understands zoning, perc, and access, not just listings.

Connect with a local land specialist

Sources

  1. Clearway Energy Group Completes Construction on Texas Wind Project (Mesquite Star) — Clearway Energy Group (accessed 2026-09)
  2. Fisher County (Texas) Wind — Blattner (accessed 2026-09)
  3. Texas Comptroller Visits Roscoe Wind Complex for Good for Texas Tour: Energy Edition — RWE (accessed 2026-09)
  4. Roscoe Wind Farm — Wikipedia (accessed 2026-09)
  5. Roscoe, Texas: Home of the World's Largest Wind Farm — Government Technology (Govtech) (accessed 2026-09)

Last reviewed 2026-09