The county hub explains that Tooele County won't issue a building permit without a documented water right. What the hub doesn't spell out is the actual sequence: getting an individual well permitted here is a multi-step process under the Health Department's own regulation, it has to happen before septic permitting can proceed, and it comes with a specific, documented protection-zone requirement around the well itself. Here's the order of operations for a parcel that doesn't already have a functioning well.

This page covers what's specific to Tooele County. For the general explanation, see the national guide.

A water right has to exist before you can even apply to drill

Individual water systems -- private wells -- in Tooele County are permitted and inspected by the Tooele County Health Department under Health Regulation #5 (Individual Water Systems). Critically, the county will not issue a permit to drill a culinary (drinking) water well until the applicant has already secured a water right and a well-driller start card from the Utah Division of Water Rights. In practical terms, this means the water-right acquisition process -- which, per the county hub, is itself constrained by Tooele Valley's closed-basin status -- is not a parallel or later step to well permitting; it's a documented prerequisite that has to be resolved first. A landowner who assumes they can drill first and sort out the water right afterward has the sequence backwards under this county's rules.

For a buyer evaluating a vacant parcel without an existing well, this means the real early-stage question isn't "can I get a well permit" -- it's "can I acquire and formally change a water right onto this specific parcel," since that's the step that unlocks everything that follows. Confirm the parcel's water-right status with a title search and directly with the Utah Division of Water Rights before assuming well permitting is a routine next step.

A documented 100-foot protection radius, and septic waits on the well

Once a well permit is in hand and drilling can proceed, Tooele County Health Department requires a 100-foot radius protection zone around the well to shield it from contamination sources -- specifically named sources include septic systems, barns, and corrals. That's a real, quantified setback that constrains how a specific parcel's well, septic system, and any planned livestock infrastructure can be laid out relative to one another; a site plan that puts a barn or septic drain field closer than 100 feet to the well location isn't a minor technicality to fix later; it's a documented Health Department standard the layout has to satisfy from the start.

The sequencing continues past the well itself: septic permits in Tooele County will not be issued until satisfactory well test results have been received. That means even after a well is drilled, water quality and yield testing has to clear before the county will move forward on the separate septic permit that a new home ultimately needs -- and the county hub's own 5-acre (or, in a narrow minor-subdivision exception, 1-acre) septic-subdivision minimum in Tooele Valley sits downstream of this well-testing gate, not ahead of it. A realistic project timeline for an undeveloped Tooele Valley parcel has to account for this full chain: water right, then well permit and drilling, then satisfactory well testing, then septic permit, then building permit.

Before assuming a timeline for an undeveloped parcel

  1. Confirm whether the parcel already has a documented water right attached, and if not, what acquiring and changing one onto the parcel would realistically involve, given Tooele Valley's closed-basin status covered on the county hub.
  2. Contact the Tooele County Health Department Environmental Health division ((435) 277-2440) for current Health Regulation #5 well-permitting requirements and the well-driller start card process with the Utah Division of Water Rights.
  3. Plan your site layout around the 100-foot well protection radius from the outset -- confirm exact setback requirements relative to any planned septic system, barn, or corral before finalizing a building or subdivision layout.
  4. Build well-testing time into your project timeline, since the county will not process a septic permit application until satisfactory well test results are on file, and the septic permit itself is a prerequisite for the building permit.
  5. Don't assume an existing well on a parcel is automatically compliant -- ask the Health Department whether the well was permitted under current Regulation #5 standards and whether documented test results are on file.

Ready to talk to someone who knows land?

Tell us what you're trying to do and we'll connect you with a local land specialist -- someone who understands zoning, perc, and access, not just listings.

Connect with a local land specialist

Sources

  1. Wells - Individual Water Systems: permitting, testing and re-certifications — Tooele County Health Department (accessed 2026-09)
  2. Applications & Fees for Environmental Health Services — Tooele County Health Department (accessed 2026-09)
  3. Environmental Health — Tooele County Health Department (accessed 2026-09)
  4. Health Regulation #12 Wastewater Disposal — Tooele County Health Department (accessed 2026-09)
  5. Area 15 - Tooele and Rush Valleys — Utah Division of Water Rights (accessed 2026-09)

Last reviewed 2026-09